Insert excerpt
Getting Started with IMOS On-Prem
Getting Started with IMOS On-Prem
nopaneltrue

...

On the Estimate Delays form, you can enter information about delays. It includes the following tabs:

Table of Contents
maxLevel1

To access the form, on the Voyage Estimate Column View or Details View menu, click Delays.

Dates Tab

The Dates tab enables you to record delays.

...

To record a delay:

  1. Add a new row.
  2. Enter the following information:
    1. ActivityDelay Type, as defined in the Data Center.
    2. ReasonDelay Reason, as defined in the Data Center.
    3. From/To dates, times, and time Zones.
      Note: If the range does not occur during the estimated itinerary, the line will appear light red.
  3. Hours automatically calculates the delay duration.
  4. Optionally, select Include in P&L to include the delay line item (e.g., unplanned off hire) in the Estimate P&L.
  5. When all delays are entered, Total shows the sum of delay hours for the Estimate.
  6. Close the Estimate Delays form.
  7. Save the Estimate.

Estimate TCE Impact

The following Activity/Reason pairs affect the Voyage Estimate TCE.

...

Insert excerpt
IMOS On-Prem - Port Functions
IMOS On-Prem - Port Functions
nopaneltrue

Bunkers Tab

The Bunkers tab enables you to record bunkers consumed during delays.

To record bunkers:

  1. Do one of the following:
    • Edit a row for an existing delay.
    • Add a row for a new delay Activity and Reason.
  2. Enter the fuel Prc and Qty consumed during the delay.
  3. Close the Estimate Delays form.
  4. Save the Estimate.