Home > Chartering > Itinerary/Options or Pricing Tab - Cargo COA
...
Load Options and Discharge Options grids: Each potential load and discharge port and the terms that apply to the port.
When you add a Port to an Options grid, the Berth defaults to Quay.
When you select a Port and Berth combination in the Itinerary that matches a Load or Discharge Option line, that information automatically populates. You can change the ports and/or terms on the Cargo form; manually overwritten values appear as blue text.
To open the Port form, for example to update berth details, right-click a Port or Port/Area row and then click Port.
Note: The suggested workflow is to update Load/Discharge options before fixing/commencing the voyage to adjust pricing.
Pricing Tab
This tab is similar to the Cargo Pricing tab.
...
Excerpt |
---|
Pricing GridTo adjust pricing, do any of the following:
|
To automatically add pricing rows based on Load/Discharge Options, click . Pricing rows are populated for any unique pair of Load and Discharge options that do not already exist in the Pricing grid. If only one Cargo is selected in the Pricing grid, the same Cargo automatically populates for each new line that is generated.
...
You can assign Extra Freight Terms to either the contract or a specific pricing row.
Do one of the following:
For the contract, add a row to the Extra Freight Terms grid.
For a pricing row, in the Xfrt column, select the check box.
Add a row for each term, select a Code and then enter a Rate/Lump amount.
Rate Tables
Freight Surcharge: To use a Freight Surcharge Table to determine the Freight Surcharge based on quantity, select Table. To edit the table, click click .
Bunker Surcharge: To use a table to determine the Bunker Surcharge, select one of the following:
Cap/Collar: Uses a Bunker Cap/Collar Table to base the surcharge on increases above a cap and decreases below a collar.
Scale Table: Uses a Bunker Surcharge Rate Table; select the table in the Table field below. To edit the table, click click .
Demurrage: Select one of the following:
Flat Rate: Enter the rates to the right.
Scale Table: Uses a Demurrage Rate Table to determine the demurrage rates based on the deadweight of the vessel; select the table in the Table field below. To edit the table, click click .
Laytime Hours: Select one of the following:
Flat Rate: Enter the Laytime Allowed amount, unit, and terms, and TT Hours.
Scale Table: Uses a Laytime Hours Rate Table to determine the laytime hours based on cargo BL quantity; select the table in the Table field below. To edit the table, click click .
Note: Pricing tab data will copy over to newly created Planning Periods from older ones as long as changes made to the contract are saved.
...