IMOS On-Prem - Port Activities Terms
Port Activities terms are used on the Port Activities form.
In the Data Center , under Ports and Areas, click Port Activities.
For each Port Activity, you can enter:
- Activities: Name of the Port Activity.
- Code: Code of up to 8 characters that can be paired with another Activity by adding its number in the Pair With column.
- Remarks:Â Free-form text field for additional information.
- Act Type: Action Type
- Pair With: Code of another Activity to use as a pair.
- Rsn Code: Delay Reason Code.
- Select check boxes for these purposes:
- Laytime Calc Import: Have a Port Activity imported into a Laytime Calculation.
- Cargo: Be able to edit the Cargo for that Port Activity.
- Charterer: On Veslink forms, be able to select a Charterer in the Port Activity control.
- Berth:Â Be able to edit the Berth for that Port Activity.
- ROBs: Add an ROBs tab to the Port Activities form for the voyage and be able to edit in-port ROBs for that Port Activity, for reporting purposes, after the date and time have been added.
Action Types
Each term can have one of the following Act (Action) Types. Only the nine Action Types mentioned in the table below have an effect in the Laytime Calculator. A typical set of Action Types for loading or discharging cargo follows:
- PS (Port Action Starts)
- NR (NOR Tendered)
- OS (Operation Starts)
- OEÂ (Operation Ends)
If there is not a matching OS to OE an error will occur - "ERROR - Port has more OE activities than OS activities“
- PE (Port Action Ends)
- IS/IE pairs (Interruption Starts/Ends) and DS/DE pairs (Delay Starts/Ends) can be inserted between OS and OE pairs to log interrupts and delays.
Action Type | Laytime Calculator Effect |
---|---|
AA = Anchor Aweigh | None |
AD = Anchor Out | None |
AF = All Fast | None |
BE = Bunkering Ends | None |
BS = Bunkering Starts | None |
CA = Free Pratique Granted | None |
CD = Cargo Documents On Board | None |
CI = Tank Inspection Completed | None |
DE = Delay Ends | Stop deducting 50% from time used |
DS = Delay Starts | Start deducting 50% from time used |
HF = Hose Disconnect Completed | None |
HN = Hose Connect Completed | None |
IE = Interruption Ends | Resume counting time |
IS = Interruption Starts | Stop counting time |
LL = Last Line | None |
NM = Normal Event | None |
NR = NOR Tendered | Laytime commenced = NOR Tendered + 6 hours |
OE = Operation Ends | Stop counting time used |
OR = Operation Resumes | None |
OS = Operation Starts | Start counting time used |
PA = Pilot On Board | None |
PE = Port Action Ends | Stop counting time used if OE was not already specified |
PO = Pilot Off | None |
PS = Port Action Starts | For verification purposes only |
RE = Rain Ends | None |
RS = Rain Starts | None |
SE = Shift Ends | None |
SS = Shift Starts | None |
XE = Dock Ends | None |
XS = Dock Starts | None |