To manage a voyage, in the Voyage Manager, do the following:

Excerpt


Step Number

Step

Anchor
key
key
 Key Information: About Voyage Status
1

Check the Validation symbol on the toolbar; if information is not complete and correct, click the symbol to see a message describing any issues.
: All information is complete.
: Some information is missing.
: The form contains one or more errors.


2

To save the voyage, click .

By default, the voyage Status is Scheduled.
3When the voyage begins, change the voyage Status from Scheduled to Commenced.When the voyage Status is changed from Scheduled to Commenced, the Status for the first port changes to Sailed.
4

As you continue through each port, right-click the port line and click Port Activities to enter Port Activities for the voyage. IMOS updates the Itinerary with any changes.


5

When you are traveling between ports, right-click the port line and click Activity Reports to track information in the Activity Reports.


6To enter Port Advances or Expenses, right-click the port line and click Port Expenses. As you enter financial information, it appears on the P&L tab.
7

To enter Voyage Other Revenues and Expenses not associated with a port or with freight, click and then click Other revenues and expenses.


8When the Start Sea Passage Port Activity is entered for the last port, IMOS changes the port Status to TE (Terminated).IMOS also changes the voyage Status to Completed. Port, bunker, cargo, and financial data can still be modified.
9After all voyage transactions are completed, change the Status to Closed.