Note: If you have purchased the separate Bunker Management module, see IMOS - Bunker Management, rather than this section.

...

Received quantities appear on the Summary tab after they are entered in IMOS - Port Activities.

To bind a Bunker Invoice to the voyage, in the Bunker Liftings grid, the S check box must be selected.

...

For voyages that are not already using Fuel Zones to calculate bunker consumption and have unsailed ports, a Use Fuel Zones button appears in the bottom right corner. To recalculate estimated bunker consumption and cost based on information entered in IMOS - Fuel Zones in the Data Center, click .

...

This form has a detail tab for each bunker grade. On each individual bunker grade tab, you can enter the Operator Quantity. The best known price is defaulted, but you can change it to maintain the P&L bunker expenses. It is the assigned price for this lifting until an invoice is issued for this lifting or a IMOS - Bunker Purchase is recorded for the port.

Req Qty is only used for a stand-alone IMOS - Bunker Requirement, and it cannot be edited because a Bunker Requirement can be linked at a later time.

...

Bunker Requirements

To enter a IMOS - Bunker Requirement, see the IMOS - Typical Operator-Only Workflow or follow the steps for an IMOS - Operator and a IMOS - Bunker Manager.

Barging

With the IMOS - Barging module, you can also do the following:

  • For Tow voyages, click  to access the IMOS - Bunker Interpolator to initiate the calculation.
  • View bunker consumption during Stop delays in the voyage, calculated by the Bunker Interpolator. It appears in the Stop column on the Summary and Detail tabs.
  • Click  and select the Bunker Interpolation Details Report.

...

Expand
titleRelated Configuration Flags


NameDescription
Disable Insufficient Bunker Warnings by Default

Enable Operations Estimate Sea Cleaning