  1. In the Voyage Manager, click  and then click Estimated Demurrage.
  2. Enter the Estimated On date.
  3. Do one of the following:
    • Enter the Rate Per DayDays Allowed, and Days Used. An Estimate of the Demurrage amount calculates.
      For a Tanker, if Days Used is less than Days Allowed, the amount is 0, unless Allow Despatch is selected on the Vessel form.
    • If days and rates are not known, enter an Estimate. The Estimate is used on the voyage P&L until your first Demurrage calculation.
  4. Do any of the following:
    • To have the voyage P&L reflect the percentage of Demurrage and Demurrage Commission you expect to be collected, enter an Accrual %.
    • To include an estimated value for Demurrage in the voyage P&L, select the Estimate is Provisional checkbox. Then the value of this Estimate is used in the Actual column until it is superseded by calculated and settled amounts; when you enter any actual amounts, they are subtracted from it.
      • For example, if the Estimate value is $100,000, and you then enter an actual amount of $50,000, the voyage P&L shows $50,000 provisional and $50,000 actual. If you enter another $60,000 actual, the voyage P&L shows $110,000 actual and no provisional Demurrage.
      • When the calculation status is Settled, the Agreed Amount is included in the voyage P&L. When the status is No Demurrage or Canceled, no demurrage or despatch is included in the voyage P&L.
      • When all Demurrage calculations are done and Claims are created, clear this checkbox, so that only calculated and settled amounts are represented in the P&L.
        Note: If the check box is not cleared when monthly accruals are run, then the Estimated Demurrage will appear under the respective Mon YYYY Accrual period of the "Compare:" drop-down in the P&L.
      • If this check box is not selected, the estimated demurrage amount is included until the first Laytime Calculation amount is included.
    • To account for the estimated time to be deducted from Days Used, include a value in Deduction From Days Used.
    • To capture notes that provide additional context for estimated demurrage calculations, include them in Remarks.
    • To synchronize the demurrage and despatch rates from the Cargo contract with the estimated demurrage rate, select the Auto-update from itinerary checkbox.

The Estimated Demurrage Amount appears on the voyage P&L. When the Laytime calculation is set to settled status, this will remove the estimated demurrage amount from the P&L (overwrite the estimated amount). Estimated Demurrage accessibility is controlled by the Voyage manager selection. (Operations > Quick Links > Voyage Manager)

...